Court Will Look To Original Contract Schedule And Surrounding Circumstances In Determining A "Reasonable" Time For Performance

INTERNATIONAL PRODUCTION SPECIALISTS v. SCHWING AMERICA, INC. (SEPTEMBER 2, 2009)

North Shore Sanitary District (NSSD) entered into a contract with Voest-Alpine Industries to build a wastewater treatment plant. Voest-Alpine in turn contracted with Schwing America to supply and install five silos and associated equipment. Schwing in turn agreed to pay International Production Specialists (IPS) almost $700,000 to fabricate and install the five silos. The original schedule provided that the silos were to be delivered by December of 2001, approximately 4 months after Schwing and IPS entered into their agreement. NSSD suspended work on the project prior to the delivery dates. Schwing instructed IPS to continue its fabrication effort with respect to the two silos with the earliest installation dates but to cease any work on the site. NSSD restarted the project two years later -- but changed the physical location of the plant. The change in location resulted in a dispute between Schwing and IPS. In fact, IPS advised Schwing that it would not complete the project. After further negotiations, the project was back on. Schwing advised IPS of a new schedule requiring installation of the first two silos in August of 2004 and the other three in December of 2004. Although IPS completed the installation of the first two silos almost on time, the other three became a problem. When the silos were still not delivered by February of 2005, Schwing terminated the contract and completed the work through other subcontractors at significant cost. IPS sued for breach of contract -- Schwing countersued. After a trial, the court concluded that Schwing both did not breach and was justified in terminating the contract. The court awarded damages of almost $500,000. IPS appeals.

In their opinion (PDF), Judges Flaum, Rovner and Williams affirmed in part and reversed in part. The Court noted that Schwing terminated the contract because of IPS's failure to satisfactorily complete the work within a specified time. If IPS's performance within a particular time was required and its failure destroyed an essential element of the contract, it would be a material breach. Under Wisconsin law, a material breach would release Schwing from its continuing performance. The Court looked to the contract. It concluded that the original agreement contained an expectation for performance within a particular time. Of course, the time frame was eliminated when NSSD put the project on hold. After the project started back up, a layout schedule contained expectations for completing the project. Considering the complexity of the project and the number of subcontractors, the Court concluded that the time frames in the layout schedule were reasonable contractual expectations. Alternatively, the Court stated that the law would imply a reasonable time for performance if the contract is silent. Given the original schedule of delivery and installation as well as the later layout schedule, the Court concluded that the schedule reflected a reasonable time for performance. Therefore, the Court agreed with the district court that IPS materially breached and that Schwing was entitled to damages. The Court also concluded that the district court did not err in its computation of damages, with one exception. At the time of IPS's breach, Schwing still owed approximately $50,000 on the contract. To put Schwing in an equivalent, but no better, position then it would have been without a breach requires it to credit IPS for the $50,000.

Trackbacks (0) Links to blogs that reference this article Trackback URL
http://www.intheiropinion.com/admin/trackback/173031
Comments (0) Read through and enter the discussion with the form at the end
Post A Comment / Question Use this form to add a comment to this entry.







Remember personal info?
Send To A Friend Use this form to send this entry to a friend via email.