SIERRA CLUB V. FRANKLIN COUNTY POWER (October 27, 2008)
In August of 2000, Franklin County Power of Illinois (“FCPI”) applied to the Illinois EPA (“IEPA”) for a Prevention of Significant Deterioration permit in order to construct a power plant. The IEPA issued the permit on July 3, 2001. The permit provided that it would become invalid if FCPI: a) did not begin construction of the plant’s boilers within eighteen months, or b) discontinued construction for eighteen months, or c) failed to complete construction within a reasonable time. On December 2, 2002, FCPI contracted with an engineering and construction company to work with it exclusively to negotiate a construction contract. On December 18, FCPI arranged for excavation to begin. Excavation equipment was delivered to the site on January 3, 2003. Although the contractor began the excavation on January 8, it terminated its work in February because of a dispute. The landlord filled in the excavation in July. FCPI began the excavation anew in September of 2004. Shortly afterward, the IEPA determined that construction had commenced. In November, the IEPA made a preliminary determination that the permit had expired. The determination was appealed and the appeal is still pending. In May of 2005, the Sierra Club filed suit under the citizen suit provision of the Clean Air Act (“CAA”). FCPI moved to dismiss and for summary judgment on the grounds that the permit was valid and that Sierra Club lacked standing. The district court denied the motion. Instead, it entered summary judgment for Sierra Club and permanently enjoined FCPI from building the power plant until it obtained a permit.
In their opinion, Judges Bauer, Ripple, and Williams affirmed. The Court first addressed Sierra Club’s standing. An organization has standing only if: a) one of its members has standing, b) the interests at stake in the litigation are germane to the organization’s purpose, and c) an individual’s participation is not required. FCPI challenged only the first prong. Sierra Club relied on its member Barbara McKasson. In order to prevail on summary judgment, Sierra Club had to submit evidence to establish that: a) she suffered an actual or imminent, concrete injury, b) the injury is traceable to the actions complained of, and c) a favorable decision would likely redress the injury. McKasson stated that she and her family have regularly traveled to within three miles of the proposed plant site and there engaged in such activities as camping, fishing, and kayaking. The Court found that Sierra Club satisfied the individual standing test: a) McKasson will either be exposed to pollutants if she continues her trips or will have to forego the trips, either of which is sufficient injury, b) the injury is actual even though the plant is not yet built, c) the injury is traceable to the plant, even if the plant reduces its emissions, and d) an injunction will redress the harm for some period of time, even if FCPI eventually obtains a new permit.
The Court next addressed FCPI’s claim that Sierra Club’s action is not ripe until IEPA issues a decision on the permit appeal. The Court said that the plain language of the CAA allows a citizen suit against a person who is alleged to be in violation of a permit or who proposes to construct without a permit. The Court found that FCPI was either in violation of the permit because it failed to commence construction in time or, if the expired permit is akin to no permit, it is proposing to build one without one. Either way, the Court found that the suit was proper under the CAA.
On the issue of whether FCPI “commenced” construction, the Court stated that FCPI could commence construction in either of two ways. It could begin “ a continuous program of physical on-site construction” or it could enter into binding contracts to complete construction within a reasonable tim. To qualify, the contracts could not be canceled without a substantial penalty. FCPI argued that there were genuine issues of fact regarding this test, precluding summary judgment. The Court had little trouble concluding that FCPI could not meet the continuous construction test. The only work it did was to excavate a hole. Even that was not permanent, since it was later filled in. The Court also found that FCPI lapsed in its construction activities for over eighteen months, even if it did begin on time. The Court also rejected FCPI’s argument that it’s binding contract meant that it had “commenced construction.” The contract was merely an agreement to negotiate in good faith in an attempt to reach an agreement on a construction contract. The fact that it contained a penalty clause was not enough to make it a qualifying contract.
Finally, FCPI argued that the district court had no authority to enter an injunction or, in the alternative, that it erred in not applying the traditional four-part analysis for injunctive relief. The Court relied on the plain language of the CAA to reject FCPI’s lack of authority argument. Although the Court was a little more troubled by the second argument, it also resolved it in Sierra Club’s favor. It first found that the lower court’s merits decision that FCPI did not have a valid permit accomplished essentially the same thing as an injunction - it required FCPI to get a permit. The Court’s also conducted its own analysis of the four factors and found that they favored Sierra Club.