Timber Sale's Environmental Impact Statement Need Not Analyze Cumulative Effects Imposed By Contemplated But Undefined Future Project

HABITAT EDUCATION CENTER v. U.S. FOREST SERVICE (June 29, 2010)

The federal government has been managing over 1,000,000 acres of forest in the Chequamegon-Nicolet National Forest in northern Wisconsin for almost 100 years. In the last eight years, the U.S. Forest Service has proposed 17 different timber sale projects. Habitat Education Center has administratively challenged almost every project. One of those projects is the Twentymile sale, announced in 2004, covering almost 9,000 acres. The Center argued that the sale, particularly in conjunction with a prior sale on immediately adjacent property, would have a negative impact on wildlife. The Forest Service authorized the project in February of 2007 over the Center's objections. The Center's administrative appeal was also unsuccessful. They filed suit in June 2007, contending that the Forest Service' environmental impact statement failed to consider the cumulative impacts of "past, present, and reasonably foreseeable future actions," in violation of the National Environmental Policy Act (NEPA). In November of 2008, just before argument on cross motions for summary judgment, the Forest Service announced another sale, the Twin Ghost project, on immediately adjacent property. Judge Adelman (E.D. Wis.) asked for supplemental briefing but ultimately concluded that the project was not "reasonably foreseeable" under NEPA at the time of the Twentymile project authorization and granted summary judgment to the Forest Service. The Center appeals.

In their opinion, Circuit Judges Flaum and Wood and District Judge St. Eve affirmed. The Court first addressed the Forest Service's argument that the Center forfeited any claim with respect to the Twin Ghost project by not raising it in the administrative process. Instead of addressing the Center's possible forfeiture, the Court concluded that the Forest Service waived the forfeiture argument by not raising it sufficiently in the district court in the supplemental briefing. On the merits, the Court noted that several of its sister circuits (specifically citing cases from the 1st, 3rd, 9th, and 11th) have held that the effects of a contemplated project need not be discussed if there is not yet a meaningful basis for assessing the impact of the project. The Court concurred with that approach. At the time the Twentymile project was approved, the Service had not even identified the goals of the Twin Ghost project. Of course, as the Court noted, the Twin Ghost project assessment must include a thorough analysis of the cumulative effects of the Twin Ghost and Twentymile projects. Any negative cumulative effects can be addressed during that process. Finally, the Court did concede that the better practice would have been for the Service to disclose the current state of contemplated future projects, even if a thorough analysis was not possible.